While not exactly a part of the campus master plan, it is nevertheless nice to see the bridge connecting the Satellite building with Chanel now covered. Students and staff will now be sheltered from rain and snow.
Gates on Vehicle Bridge
by Marist School on 10. Mar, 2012 in Bridges, Construction
The
gates on the vehicle bridge were installed this week. This bridge and the other two pedestrian bridges are now complete. All of the gates on the bridges will remain closed and locked at this time. Even though the development of this portion of the campus is nearly complete, we are awaiting the final approval of DeKalb County before the property can be opened and used. Everyone is asked to please remain off of the property until it is officially opened in early April (we hope!).
Bridge to Distant Athletic Practice Field
by Marist School on 06. Mar, 2012 in Bridges
The pedestrian bridge leading to the distant athletic practice field has been completed. All of the bridges are designed to be closed during flood events. The maintenance and security crews have access to Marist School’s Emergency Flood Plan to instruct them when the athletic fields and parking lots are to be closed and the gates on the bridges are to be locked.
Powered Up
by Marist School on 04. Mar, 2012 in Bridges, Parking
All of the lights have been installed on the parking lots, bridges and drives. Most are in working order. The lights will be operated on the photocells for several days to complete their programming. Following this test period, they will be controlled also by a timer which will set some zones to be turned off when those sections are not being used.
Pedestrian Bridge Completed
by Marist School on 02. Mar, 2012 in Bridges
Brick Surface on Bridge Columns
by Marist School on 29. Feb, 2012 in Bridges
The final layer of bricks was laid on the columns of the pedestrian bridge. The color of the brick and the patterns match those used on the front entrance of the campus.
Brick facade added to Bridge Columns
by Marist School on 17. Feb, 2012 in Bridges
The four columns on each of the bridges are designed to support the cable railing and lamp posts. The columns will receive a brick facade to match the campus entrance. The bricks are being applied this week to the pedestrian bridge near the main campus parking lot.
Lamp Posts Planted
by Marist School on 15. Feb, 2012 in Bridges, Landscape, Parking
Lamp posts are being installed. Those on the main campus are already in place. The remainder will be installed through the rest of the month.
There is a lot of additional activity today:
- The cable rails for the vehicle bridge are being installed;
- The brick facing is being added to the columns on the pedestrian bridge;
- The mounds installed to allow construction equipment to drive over the pipelines for access to the athletic fields has been removed;
- The pavers are being installed in the traffic circles;
- Landscaping is being done in the area between the lower parking lot and Nancy Creek.
- The upper parking lot is being prepared for its pervious paving which occurs later this week.
Cable Rails on Bridges
by Marist School on 11. Feb, 2012 in Bridges
Concrete Decks Poured
by Marist School on 26. Jan, 2012 in Bridges
The concrete decks for the vehicle bridge and the pedestrian bridges have been poured.
Master Plan Key Dates
Sep 19:
Cross Creek Construction Begins
Oct 3 - 7:
Demolition of Empty Ashdun Hall
Oct 7 - Nov 11
Bridge Caissons Installed
Apr 4
Dedication Ceremony of Cross Creek Property
May 29
Chapel Closes for Renovation
May 30 - Jun 1
Asbestos Abatement in Chapel
Aug 22
New Parking Rules become Effective
Sep 21
Fine Arts Entrance Re-opens
Sep 27
Fine Arts Completed
Oct 4
Chapel Renovation Substantially Completed
Oct 22
New Moo Completed
Blog Categories
Posts By Date
| S | M | T | W | T | F | S |
|---|---|---|---|---|---|---|
| « Oct | ||||||
| 1 | 2 | 3 | 4 | |||
| 5 | 6 | 7 | 8 | 9 | 10 | 11 |
| 12 | 13 | 14 | 15 | 16 | 17 | 18 |
| 19 | 20 | 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 | 31 | |



